SCHEDULE 9Protective provisions
PART 11For the protection of Phillips 66 Limited
Authorisation of works details affecting pipelines or protected crossings
schedule 9 paragraph 144 144.—(1) Before commencing any part of a relevant work the undertaker must submit the works details to P66 in accordance with paragraph 145.
(2) The works details submitted under sub-paragraph (1) will be treated as having been received by P66 on the date—
schedule 9 paragraph 144 2 a (a)that the undertaker obtains written acknowledgement of receipt from P66; or
schedule 9 paragraph 144 2 b (b)two clear working days following the date that the work details were submitted under sub-paragraph (1),
whichever is earliest.
(3) The undertaker must as soon as reasonably practicable provide such further particulars as P66 may, within 30 days from the receipt of the works details under sub-paragraph (2), reasonably require.