SCHEDULE 9Protective provisions
PART 9For the protection of National Highways Limited
Indemnity
schedule 9 paragraph 123 123.—(1) The undertaker fully indemnifies National Highways from and against all costs, claims, expenses, damages, losses and liabilities suffered by National Highways arising from the construction, maintenance or use of the specified works or exercise of or failure to exercise any power under this Order within 30 days of demand.
(2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to—
schedule 9 paragraph 123 2 a (a)any loss arising out of or in consequence of any negligent act or default of National Highways or its officers servants agents or contractors or any person or body for which it is responsible; or
schedule 9 paragraph 123 2 b (b)any indirect or consequential loss of National Highways or any third party (including but not limited to loss of use, revenue, profit, contract, production, increased cost of working or business interruption).