SCHEDULE 2Requirements
PART 1Requirements
Construction environmental management plan
schedule 2 paragraph 5 5.—(1) No stage of the authorised development may commence until a CEMP which includes that stage has been submitted to and approved by the relevant planning authority following consultation with the Environment Agency and Lincolnshire County Council.
(2) The CEMP must be substantially in accordance with the outline construction environment management plan and include management plans, working methods and mitigation measures including—
schedule 2 paragraph 5 2 a (a)details of lighting during construction;
schedule 2 paragraph 5 2 b (b)noise and vibration management plan;
schedule 2 paragraph 5 2 c (c)dust management plan;
schedule 2 paragraph 5 2 d (d)materials management plan;
schedule 2 paragraph 5 2 e (e)soil management plan;
schedule 2 paragraph 5 2 f (f)water management plan;
schedule 2 paragraph 5 2 g (g)site waste management plan;
schedule 2 paragraph 5 2 h (h)emergency response plan;
schedule 2 paragraph 5 2 i (i)stakeholder communication plan;
schedule 2 paragraph 5 2 j (j)public right of way management plan;
schedule 2 paragraph 5 2 k (k)construction ecological management plan;
schedule 2 paragraph 5 2 l (l)species protection plans; and
schedule 2 paragraph 5 2 m (m)invasive non-native species method statement.
(3) Each stage of the authorised development must be undertaken in accordance with the approved CEMP for that stage, or with such changes to that document as approved by the relevant planning authority.