ID badges: Hide | Show

SCHEDULES

SCHEDULE 17COMPENSATON TO PROTECT THE COHERENCE OF THE NATIONAL SITE NETWORK

PART 1KITTIWAKE COMPENSATION

schedule 17 paragraph 3 3.  Where the undertaker elects to submit a Final KIMP no offshore works are to commence until a plan for the work of the OKEG has been submitted to and approved by the Secretary of State, such plan to include—

schedule 17 paragraph 3 a (a)the identity of, or the arrangements for establishment of, the OKEG;

schedule 17 paragraph 3 b (b)its terms of reference;

schedule 17 paragraph 3 c (c)its membership shall (as a minimum) include the local planning authority for the area in which the onshore kittiwake compensation measure is to be provided and statutory nature conservation body as core members and the Royal Society for the Protection of Birds as advisory member;

schedule 17 paragraph 3 d (d)details of the proposed schedule of meetings, reporting and review periods;

schedule 17 paragraph 3 e (e)the dispute resolution mechanism and confidentiality provisions; and

schedule 17 paragraph 3 f (f)a schedule of preparation and delivery.