SCHEDULE 17COMPENSATON TO PROTECT THE COHERENCE OF THE NATIONAL SITE NETWORK

PART 2GUILLEMOT COMPENSATION

schedule 17 paragraph 16 16.  The Final GCIMP (if required) must be based on the strategy for guillemot compensation set out in the guillemot implementation and monitoring plan and include—

schedule 17 paragraph 16 a (a)the location where the compensation measures will be delivered and the suitability of that location (including why the location is appropriate ecologically and likely to support successful compensation), and confirmation that the necessary landowner agreement(s) are in place;

schedule 17 paragraph 16 b (b)an implementation timetable for delivery including any arrangements made with a third party for implementation of the measures;

schedule 17 paragraph 16 c (c)details of any contribution to be made to a third party to ongoing maintenance of the compensation measures delivered in collaboration with a third party;

schedule 17 paragraph 16 d (d)details for the ongoing monitoring and reporting of the effectiveness of the compensation measures identified in the Final GCIMP including—

schedule 17 paragraph 16 d i (i)survey methods;

schedule 17 paragraph 16 d ii (ii)survey programmes;

schedule 17 paragraph 16 d iii (iii)success criteria; and

schedule 17 paragraph 16 d iv (iv)timescales for the monitoring reports to be delivered;

schedule 17 paragraph 16 e (e)details of any adaptive management measures, with details of the factors used to trigger any alternative and/or adaptive management measures; and

schedule 17 paragraph 16 f (f)confirmation as to how it has had regard to output of consultation with OGEG.