Reporting of cable protection
schedule 12 paragraph 23 23.—(1) Not more than four months following completion of the construction phase of the project, the undertaker must provide the MMO and the statutory nature conservation body with a report setting out details of the cable protection used for the authorised scheme.
(2) The report is to include the following information—
schedule 12 paragraph 23 2 a (a)location of the cable protection;
schedule 12 paragraph 23 2 b (b)volume of cable protection; and
schedule 12 paragraph 23 2 c (c)any other information relating to the cable protection as agreed between the MMO and the undertaker.