SCHEDULE 11DEEMED MARINE LICENCE UNDER THE 2009 ACT—GENERATION ASSETS

PART 2CONDITIONS

Design parameters

schedule 11 part 2 paragraph 2 2.—(1) The total length of the array cables comprising Work No. 2 must be no more than 250 kilometres.

(2) The total volume of cable protection comprising Work No. 2 must be no more than 175,000 cubic metres with a maximum footprint of 300,000 square metres.

(3) The number of cable crossings comprising Work No. 2 must be no more than four unless otherwise agreed with the MMO.

(4) The maximum area impacted by cable crossings must be no more than 10,000 square metres.

(5) The total volume of cable protection for cable crossings must be no more than 20,000 cubic metres (pre- and post-lay).

(6) Any cable protection authorised under this licence must be deployed within 10 years from the commencement of the authorised scheme unless otherwise agreed in writing with the MMO.

(7) The array cables comprising Work No. 2 must be installed using one or more of the following installation methods: ploughing, trenching or jetting and are to be installed at a target burial depth of 1 metre below seabed surface.