ID badges: Hide | Show

SCHEDULES

SCHEDULE 11DEEMED MARINE LICENCE UNDER THE 2009 ACT—GENERATION ASSETS

PART 2CONDITIONS

Updating of cable monitoring plan

schedule 11 paragraph 21 21.  Following installation of array cables, the cable monitoring plan required under condition 11(1)(n)(v) must be updated with the results of the post-installation surveys. The plan must be implemented during the operational lifetime of the project and reviewed as specified within the plan, following cable burial surveys, or as instructed in writing by the MMO.