SCHEDULE 10PROTECTIVE PROVISIONS

PART 4FOR THE PROTECTION OF SOUTHERN ELECTRIC POWER DISTRIBUTION PLC AS ELECTRICITY UNDERTAKER

Interpretation

schedule 10 part 4 paragraph 2 2.  In this Part of this Schedule—

term alternative apparatus alternative apparatus” means appropriate alternative apparatus to the reasonable satisfaction of SSE to enable SSE to fulfil its statutory functions in a manner no less efficient than previously;

term apparatus apparatus” means any electric lines or electrical plant as defined in the Electricity Act 1989 belonging to or maintained by SSE;

term authorised works authorised works” has the same meaning as is given to the term “authorised development” in article 2 of this Order and includes any associated development authorised by the Order and for the purposes of this Part of this Schedule includes the use and maintenance of the authorised works and construction of any works authorised by this Schedule;

term commence commence” has the same meaning as in article 2 of this Order and commencement shall be construed to have the same meaning save that for the purposes of this Part of this Schedule the terms commence and commencement include operations consisting of archaeological investigations, intrusive investigations for the purpose of assessing ground conditions, and remedial work in respect of any contamination or other adverse ground conditions;

term functions functions” includes powers and duties;

term ground mitigation scheme ground mitigation scheme” means a scheme approved by SSE (such approval not to be unreasonably withheld or delayed) setting out the necessary measures (if any) for a ground subsidence event;

term ground monitoring scheme ground monitoring scheme” means a scheme for monitoring ground subsidence which sets out the apparatus which is to be subject to such monitoring, the extent of land to be monitored, the manner in which ground levels are to be monitored, the timescales of any monitoring activities and the extent of ground subsidence which, if exceeded, shall require the undertaker to submit for SSE’s approval a ground mitigation scheme;

term ground subsidence event ground subsidence event” means any ground subsidence identified by the monitoring activities set out in the ground monitoring scheme that has exceeded the level described in the ground monitoring scheme as requiring a ground mitigation scheme;

“in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;

“maintain” and “maintenance” shall include the ability and right to do any of the following in relation to any apparatus or alternative apparatus of SSE including to construct, inspect, maintain, use, repair, renew or remove the apparatus;

“plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe and assess the works to be executed;

term parent company parent company” means a parent company of the undertaker acceptable to SSE and which shall have been approved by SSE acting reasonably;

“rights” shall include rights and restrictive covenants and, in relation to decommissioned apparatus, the surrender of rights, release of liabilities and transfer of decommissioned apparatus;

term sse SSE” means Southern Electric Power Distribution plc (company number 04094290 whose registered office is at No. 1 Forbury Place, 43 Forbury Road, Reading, United Kingdom, RG1 3JH) or its successors in title or successor bodies and/or any successor as an electricity distribution licence holder pursuant to the Electricity Act 1989;

term sses undertaking SSE’s undertaking” means the rights, duties and obligations of SSE as an electricity distribution licence holder within the meaning of the Electricity Act 1989;

term specified works specified works” means any of the authorised works or activities undertaken in association with the authorised works which—

(a)

will or may be situated over, or within, 15 metres measured in any direction of any apparatus, the removal of which has not been required by the undertaker under sub-paragraph 6(2) or otherwise; and/or

(b)

may in any way adversely affect any apparatus, the removal of which has not been required by the undertaker under sub-paragraph 6(2) or otherwise.