Site-specific plan for the detailed design approval of the onshore substation at Oakendene

schedule 1 paragraph 8 8.—(1) No stage which includes works comprising any part of Work No. 16 and Work No. 18, together with the parts of Work No. 17 associated with those works, accesses A61 and A64 as shown on sheet 33 of the access rights of way and streets plans at Kent Street, or establishment and use of either of the compounds comprising Work No. 10 shown on sheet 33 of the onshore works plans (excluding any onshore site preparation works) must commence, only insofar as such works are included within or relate to works within that stage until—

schedule 1 paragraph 8 1 a (a)the following details of the substation (Work No.16)—

schedule 1 paragraph 8 1 a i (i)siting and layout;

schedule 1 paragraph 8 1 a ii (ii)scale and quantum of development and its uses;

schedule 1 paragraph 8 1 a iii (iii)existing and proposed finished ground levels;

schedule 1 paragraph 8 1 a iv (iv)landscaping;

schedule 1 paragraph 8 1 a v (v)access (Work No. 18); and

schedule 1 paragraph 8 1 a vi (vi)external appearance, form and materials for any buildings structures and other infrastructure including boundary treatment,

schedule 1 paragraph 8 1 b (b)a single comprehensive traffic management and access plan covering—

schedule 1 paragraph 8 1 b i (i)the programming and routing of construction traffic along the A272 and into and out of the compounds comprising Work No. 10 shown on sheet 33 of the onshore works plans and Kent Street;

schedule 1 paragraph 8 1 b ii (ii)the safety of construction accesses off the A272 and Kent Street;

schedule 1 paragraph 8 1 b iii (iii)the safety of non-construction traffic, pedestrians, cyclists and equestrians using Kent Street;

schedule 1 paragraph 8 1 b iv (iv)the restriction of HGV traffic from unsuitable routes off the A272;

schedule 1 paragraph 8 1 b v (v)measures to minimise the volume of construction traffic passing through the Air Quality Management Area at Cowfold;

schedule 1 paragraph 8 1 b vi (vi)traffic management measures in respect of any previous stage approved under this requirement; and

schedule 1 paragraph 8 1 c (c)details of vegetation removal, retention and replanting within Work Nos. 16 and 18 and along Kent Street at construction accesses A61 and A64 as shown on sheet 33 of the access rights of way and streets plans, which must be consistent with the outline landscape and ecology management plan;

have been submitted to and approved in writing by the relevant planning authority following consultation with the highway authority and West Sussex Fire and Rescue Service and works covered by the details submitted under this sub-paragraph (1) must be carried out in accordance with the approved details.

(2) Where details are approved pursuant to sub-paragraph (1) then details for—

schedule 1 paragraph 8 2 a (a)construction traffic management;

schedule 1 paragraph 8 2 b (b)accesses A61 and A64 as shown on sheet 33 of the access rights of way and streets plans;

schedule 1 paragraph 8 2 c (c)vegetation removal, retention and replanting for the part of the stage for which approval has been secured under sub-paragraph 8(1);

shall not be required to be approved under requirements 12, 13, 15 or 24 as applicable.

(3) Any details provided by the undertaker pursuant to sub-paragraph (1) must accord with the principles set out in the relevant part of the design and access statement including taking account of climate change allowances, relationship to and effect on heritage assets, must accord with the drainage arrangements approved pursuant to requirement 17, include details of any water harvesting and recycling measures and be within the Order limits.

(4) The details submitted pursuant to sub-paragraph (3) must demonstrate how the operation of Work No. 16 will secure water neutrality.

(5) To the extent comprised in Work No. 16—

schedule 1 paragraph 8 5 a (a)there must be no more than 12 buildings;

schedule 1 paragraph 8 5 b (b)the height of the main operational building and other infrastructure must be no more than 28.75 metres above ordnance datum;

schedule 1 paragraph 8 5 c (c)the maximum main building length must be no more than 70 metres;

schedule 1 paragraph 8 5 d (d)the maximum main building width must be no more than 20 metres;

schedule 1 paragraph 8 5 e (e)lightning protection masts must be no more than a height of 34.25 metres above ordnance datum; and

schedule 1 paragraph 8 5 f (f)the maximum height of any fire walls must be no more than 26.25 metres above ordnance datum.

(6) For the purposes of paragraph (4) the term ‘water neutrality’ means that the use of water in the supply area before the development of Work No. 16 is the same or lower after the development is in place in order to meet the requirements of regulation 63 of the Conservation of Habitats and Species Regulations 2017.

(7) For the purposes of paragraph (5) the term ‘building’ excludes electrical infrastructure installations.