ID badges: Hide | Show

SCHEDULES

SCHEDULE 1AUTHORISED PROJECT

PART 3REQUIREMENTS

Detailed offshore design parameters

schedule 1 paragraph 4 4.  The total volume of scour protection comprising development associated with the offshore substations comprising Work No. 3 must be no more than 65,700 cubic metres with a maximum footprint of 21,900 square metres.