SCHEDULES
SCHEDULE 1AUTHORISED PROJECT
PART 3REQUIREMENTS
Detailed offshore design parameters
schedule 1 paragraph 3 3.—(1) There must be no more than 3 offshore substations.
(2) The dimensions of any offshore substation must be no more than—
schedule 1 paragraph 3 2 a (a)65 metres in height when measured from LAT and 115 metres in height with lightning protection and ancillary structures;
schedule 1 paragraph 3 2 b (b)80 metres in length; and
schedule 1 paragraph 3 2 c (c)50 metres in width.
(3) There must be no offshore substation located within 500 metres of the array periphery.
(4) Offshore substation foundation structures must comprise either monopile foundations or multileg foundations.
(5) Offshore substation installations with—
schedule 1 paragraph 3 5 a (a)multileg foundation employing pin piles forming part of the authorised project must have—
schedule 1 paragraph 3 5 a i (i)no more than 6 legs per foundation;
schedule 1 paragraph 3 5 a ii (ii)no more than 12 pin piles per foundation; and
schedule 1 paragraph 3 5 a iii (iii)a pin pile diameter of no greater than 4.5 metres; and
schedule 1 paragraph 3 5 b (b)monopile foundation forming part of the authorised project must have a diameter no greater than 13.5 metres.