SCHEDULES
SCHEDULE 1AUTHORISED PROJECT
PART 3REQUIREMENTS
Code of construction practice
schedule 1 paragraph 22 22.—(1) No stage of any works landward of MLWS may commence until a detailed code of construction practice for the stage has been submitted to and approved by the relevant planning authority, following consultation with the Environment Agency, the statutory nature conservation body, the highway authority and the lead local flood authority and, to the extent that it relates to works seaward of mean high water springs comprising Work No. 6, the MMO.
(2) Any construction code of practice submitted under sub-paragraph (1) may cover one or more stage of the works landward of MLWS.
(3) All construction works landwards of MLWS must be undertaken in accordance with the relevant approved code of construction practice.
(4) The code of construction practice must accord with the outline code of construction practice and include, as appropriate to the relevant stage—
schedule 1 paragraph 22 4 a (a)arboricultural method statement and tree protection plan;
schedule 1 paragraph 22 4 b (b)construction phase drainage plan;
schedule 1 paragraph 22 4 c (c)materials management plan;
schedule 1 paragraph 22 4 d (d)site waste management plan which accords with the outline site waste management plan;
schedule 1 paragraph 22 4 e (e)soil management plan which accords with the outline soils management plan;
schedule 1 paragraph 22 4 f (f)biodiversity management plan including invasive non-native species protocol;
schedule 1 paragraph 22 4 g (g)noise and vibration management plan (construction) which accords with the outline noise and vibration management plan;
schedule 1 paragraph 22 4 h (h)air quality management plan which accords with the outline air quality management plan;
schedule 1 paragraph 22 4 i (i)emergency response plan;
schedule 1 paragraph 22 4 j (j)pollution prevention plan and pollution incident response plan;
schedule 1 paragraph 22 4 k (k)details for dealing with contaminated land and groundwater;
schedule 1 paragraph 22 4 l (l)arrangements for temporary fencing or other means of secure enclosure of the construction sites and compounds during the carrying out of the connection works and their removal on their completion;
schedule 1 paragraph 22 4 m (m)details for dealing with artificial light emissions (construction);
schedule 1 paragraph 22 4 n (n)hours of construction working; and
schedule 1 paragraph 22 4 o (o)water quality monitoring programme.