SCHEDULES
SCHEDULE 1AUTHORISED PROJECT
PART 3REQUIREMENTS
Stages of onshore works
schedule 1 paragraph 10 10.—(1) No part of the authorised project within the Order limits landward of MLWS excluding onshore site preparation works is to commence until a written programme identifying the stages of those works has been submitted to and approved by the relevant planning authorities and to the extent that it relates to works seaward of mean high water springs comprising Work No. 6 following consultation with the MMO.
(2) No onshore site preparation works is to commence until a written programme identifying the stages of those onshore site preparation works has been submitted to and approved by the relevant planning authorities and to the extent that it relates to works seaward of mean high water springs comprising Work No. 6 following consultation with the MMO.
(3) The authorised project must be implemented in stages as approved and each reference to a stage in these requirements is a reference to a stage in the programme as so approved.