ID badges: Hide | Show

PART 2PRINCIPAL POWERS

Interaction with the Rampion Offshore Wind Farm Order 2014

article 7 7.—(1) As from the date of this Order the provisions of the Rampion Offshore Wind Farm Order 2014(1) is amended as follows.

(2) For article 3 (Development consent etc granted by the Order) substitute—

3.(1) Subject to the provisions of this Order and to the requirements the undertaker is granted—

(a)development consent for the authorised development; and

(b)consent for the ancillary works,

to be carried out within the Order limits.

(2) Subject to article 3(3) and the requirements, Work Nos. 1 to 3A may be constructed anywhere within the Order limits seaward of MHWS and Work Nos. 3B to 32 may be constructed anywhere within the Order limits landward of MLWS.

(3) Notwithstanding article 3(1) no more than—

(a)116 wind turbine generators; and

(b)1 offshore substation,

may be constructed pursuant to this Order unless the development authorised by the Rampion 2 Offshore Wind Farm Order 2025 has not been commenced by no later than the date on which the powers under the Rampion 2 Offshore Order 2025 expire in accordance with Requirement 1 of Part 3 of Schedule 1 and the right to do so has expired.