SCHEDULES
SCHEDULE 8PROTECTIVE PROVISIONS
PART 6FOR THE PROTECTION OF LOCAL HIGHWAY AUTHORITIES
Provisional certificate
schedule 8 paragraph 62 62.—(1) Subject to sub-paragraph (2), when the undertaker considers that the specified works have reached completion so that they are available for use by the public it must apply to the relevant highway authority for a provisional certificate and must allow the relevant highway authority the opportunity to inspect the specified works to identify any defects or incomplete works (and the undertaker must make good such defects pursuant to paragraph 60 (defects in local highways constructed by the undertaker).
(2) Following an application for a provisional certificate, the relevant highway authority must as soon as reasonably practicable—
schedule 8 paragraph 62 2 a (a)inspect the specified works; and
schedule 8 paragraph 62 2 b (b)provide the undertaker with a written list of any works that are required for the provisional certificate to be issued or confirmation that no further works are required for this purpose.
(3) When—
schedule 8 paragraph 62 3 a (a)a stage 3 road safety audit has been carried out in respect of the works in question and any recommended measures identified in the audit have been completed and approved by the relevant highway authority;
schedule 8 paragraph 62 3 b (b)the relevant highway authority has been provided an opportunity to inspect the specified works and the undertaker has completed any further works or measures required to address any safety deficiencies or defects identified as a result of the inspection to the reasonable satisfaction of the relevant highway authority; and
schedule 8 paragraph 62 3 c (c)the undertaker has paid the commuted sum to the relevant highway authority,
the relevant highway authority must promptly issue the provisional certificate to the undertaker.
(4) The undertaker must submit a stage 4 road safety audit as required by and in line with the timescales stipulated in the road safety audit standard.
(5) The undertaker must comply with the findings of the stage 4 road safety standard and must pay all reasonable costs of and incidental to such and provide updated as-built information to the relevant highway authority.