SCHEDULE 8PROTECTIVE PROVISIONS

PART 6FOR THE PROTECTION OF LOCAL HIGHWAY AUTHORITIES

Inspections and testing of materials

schedule 8 paragraph 59 59.—(1) The undertaker must allow and facilitate an appropriately qualified officer or officers of a relevant highway authority that have been nominated by that relevant highway authority (each being a “nominated officer”) to access and inspect at all reasonable times any part of the specified works during their construction and before a final certificate has been issued in respect of the specified works as is reasonably necessary to ensure that the works have been or are being carried out to the appropriate standard.

(2) Any testing reasonably requested by the relevant highway authority of materials used in any specified works must be carried out at the undertaker’s expense and in accordance with the DMRB (or any other testing specification agreed by the undertaker and the relevant highway authority acting reasonably).

(3) A relevant highway authority (or its agent) may test all or any materials used or proposed to be used in any specified works and the undertaker must provide such information, access and materials as is reasonably required to facilitate such testing.

(4) The undertaker must, as soon as is reasonably practicable, provide the relevant highway authority with a copy of all test certificates and results relevant to the specified works that the relevant highway authority has requested in writing

(5) The relevant highway authority must as soon as is reasonably practicable provide the undertaker with a copy of all test results and certificates relevant to the works that the undertaker has requested in writing.

(6) In circumstances where any relevant work carried out by the undertaker is tested by the relevant highway authority pursuant to the provisions of this Part of this Schedule that test resulted in works being undone at the undertaker’s expense (acting reasonably) and found to be satisfactory then that expense must forthwith be reimbursed by the relevant highway authority provided that the relevant highway authority was given a reasonable opportunity by the undertaker to inspect the works at a time when the works could have been inspected without the need to incur the expense.

(7) If any part of the specified works is constructed—

schedule 8 paragraph 59 7 a (a)other than in accordance with the requirements of this Part of this Schedule; or

schedule 8 paragraph 59 7 b (b)in a way that causes damage to the highway, highway structure or asset or any other land of the relevant highway authority,

the relevant highway authority may by notice in writing require the undertaker, at the undertaker’s own expense, to comply promptly with the requirements of this Part of this Schedule or remedy any damage notified to the undertaker under this Part of this Schedule, to the reasonable satisfaction of the relevant highway authority.

(8) If during the carrying out of the authorised development the undertaker or its appointed contractors or agents causes damage to the local highway then the relevant highway authority may by notice in writing require the undertaker, at its own expense, to remedy the damage.

(9) If within 28 days on which a notice under sub-paragraph (7) or sub-paragraph (8) is served on the undertaker (or in the event of there being, in the opinion of the relevant highway authority, a danger to highway users, within such lesser period as the relevant highway authority may stipulate), the undertaker has failed to take the steps required by that notice, the relevant highway authority may carry out the steps required of the undertaker and may recover any expenditure incurred by the relevant highway authority in so doing, such sum to be payable within 30 days of demand.