SCHEDULE 8PROTECTIVE PROVISIONS
PART 7FOR THE PROTECTION OF RAILWAY INTERESTS
Approval of plans
schedule 8 paragraph 78 78. The undertaker must repay to Network Rail all reasonable fees, costs, charges and expenses reasonably incurred by Network Rail—
schedule 8 paragraph 78 a (a)in constructing any part of a specified work on behalf of the undertaker as provided by paragraph 73(3) or in constructing any protective works under the provisions of paragraph 73(4) including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;
schedule 8 paragraph 78 b (b)in respect of the approval by the engineer of plans submitted by the undertaker and the supervision by the engineer of the construction of a specified work;
schedule 8 paragraph 78 c (c)in respect of the employment or procurement of the services of any inspectors, signallers, watch-persons and other persons whom it is reasonably necessary to appoint for inspecting, signalling, watching and lighting railway property and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of a specified work;
schedule 8 paragraph 78 d (d)in respect of any special traffic working resulting from any speed restrictions which may in the opinion of the engineer, require to be imposed by reason or in consequence of the construction or failure of a specified work or from the substitution or diversion of services which may be reasonably necessary for the same reason; and
schedule 8 paragraph 78 e (e)in respect of any additional temporary lighting of railway property in the vicinity of the specified works, being lighting made reasonably necessary by reason or in consequence of the construction or failure of a specified work.