SCHEDULES
SCHEDULE 8PROTECTIVE PROVISIONS
PART 6FOR THE PROTECTION OF LOCAL HIGHWAY AUTHORITIES
Defects in local highways constructed by the undertaker
schedule 8 paragraph 60 60.—(1) Until such time as a final certificate has been issued in respect of any specified works, the undertaker must make good any defects in the specified works constructed by the undertaker to the reasonable satisfaction of the relevant highway authority.
(2) The undertaker must submit to the relevant highway authority such details and information relating to making good any defects under sub-paragraph (1) as the relevant highway authority and the undertaker agree is reasonable in the circumstances.