SCHEDULES
SCHEDULE 8PROTECTIVE PROVISIONS
PART 6FOR THE PROTECTION OF LOCAL HIGHWAY AUTHORITIES
Detailed design information and commencement
schedule 8 paragraph 55 55. Before commencing any specified works, the undertaker must—
schedule 8 paragraph 55 a (a)provide to the relevant highway authority the detailed design information relating to those specified works and obtain the relevant highway authority’s written approval for those works; and
schedule 8 paragraph 55 b (b)secure road space booking from the relevant highway authority, such road space booking approval not to be unreasonably withheld or delayed.