ID badges: Hide | Show

SCHEDULES

SCHEDULE 8PROTECTIVE PROVISIONS

PART 5FOR THE PROTECTION OF NATIONAL HIGHWAYS LIMITED

Security

schedule 8 paragraph 47 47.  The specified works must not commence until—

schedule 8 paragraph 47 a (a)the undertaker procures that the specified works are secured by a bond from a bondsman first approved by National Highways in the agreed form between the undertaker and National Highways to indemnify National Highways against all losses, damages, costs or expenses arising from any breach of any one or more of the obligations of the undertaker in respect of the exercise of the powers under this Order and the specified works under the provisions of this Part of this Schedule provided that the maximum liability of the bond must not exceed the bond sum; and

schedule 8 paragraph 47 b (b)the undertaker has provided the cash surety which may be utilised by National Highways in the event of the undertaker failing to meet its obligations to make payments under paragraph 41 (payments) or to carry out works the need for which arises from a breach of one or more of the obligations of the undertaker under the provisions of this Part of this Schedule.