ID badges: Hide | Show

SCHEDULES

SCHEDULE 2REQUIREMENTS

PART 2REQUIREMENTS PERTAINING TO CONSTRUCTION

Code of Construction Practice

schedule 2 paragraph 8 8.—(1) The authorised development must be carried out in accordance with the code of construction practice and with the management plans approved under sub-paragraphs (2) and (3).

(2) No part of the authorised development may commence until the following management plans have been developed for that part, substantially in accordance with the outlines of those plans referred to or provided in the code of construction practice, and approved in writing by the relevant planning authority in consultation with other consultees that the relevant planning authority consider appropriate—

schedule 2 paragraph 8 2 a (a)framework materials management plan;

schedule 2 paragraph 8 2 b (b)carbon efficiency plan;

schedule 2 paragraph 8 2 c (c)construction surface water management strategy;

schedule 2 paragraph 8 2 d (d)construction noise and vibration management plan;

schedule 2 paragraph 8 2 e (e)community engagement plan;

schedule 2 paragraph 8 2 f (f)emergency plan;

schedule 2 paragraph 8 2 g (g)pollution incident control plan;

schedule 2 paragraph 8 2 h (h)dust management plan;

schedule 2 paragraph 8 2 i (i)site waste management plan (to be substantially in accordance with the outline site waste management plan); and

schedule 2 paragraph 8 2 j (j)soil management plan (to be substantially in accordance with the outline soil management plan).

(3) No part of the authorised development may commence until a construction site lighting plan for that part, substantially in accordance with the lighting measures contained in the code of construction practice, and including detailed measures to minimise light spillage, has been submitted to and approved in writing by the relevant planning authority in consultation with the specified authorities and the relevant highway authority.