SCHEDULE 2REQUIREMENTS

PART 2REQUIREMENTS PERTAINING TO CONSTRUCTION

Detailed design

schedule 2 paragraph 6 6.—(1) No part of the authorised development is to commence until an application containing the detailed design of that part has been submitted to and approved in writing by the relevant planning authority.

(2) The application referred to in sub-paragraph (1) must include the following details—

schedule 2 paragraph 6 2 a (a)plans, sections and supporting information showing the detailed layout, siting, scale, levels (including where relevant finished floor levels) and external appearance of any buildings, structure and other works;

schedule 2 paragraph 6 2 b (b)identification of the specific Schedule 1 works (or part of works), including the components described in those works, which comprise the part of the authorised development for which the detailed design approval is being sought;

schedule 2 paragraph 6 2 c (c)for any works within the airport—

schedule 2 paragraph 6 2 c i (i)a plan which identifies the location and extent of the specific Schedule 1 works in relation to the scheme layout plans, and identifies any other parts of the scheme layout plans for which an approval under sub-paragraph (1) has already been obtained; and

schedule 2 paragraph 6 2 c ii (ii)a statement identifying the current passenger throughput of the airport, in million passengers per annum, and an indicative estimate of the amount of any passenger throughput increase, if any, expected to be facilitated by implementation of that part of the authorised development and the indicative timescales for realising that increase in throughput;

schedule 2 paragraph 6 2 d (d)information to demonstrate that the works comply with the dimensions and levels contained in the table in paragraph 7 (parameters of authorised development) of this Schedule, where applicable;

schedule 2 paragraph 6 2 e (e)in respect of Works Nos. 3b(01), 3b(02), 3d, 3f, 3g and 4a, a report setting out—

schedule 2 paragraph 6 2 e i (i)the design approach;

schedule 2 paragraph 6 2 e ii (ii)how the design principles have been incorporated into the final design; and

schedule 2 paragraph 6 2 e iii (iii)how the output of the design review process has been taken into account in the design presented for approval;

schedule 2 paragraph 6 2 f (f)an indicative programme for the implementation of the works;

schedule 2 paragraph 6 2 g (g)an operational lighting scheme for any building, structure or other works for that part, including detailed measures to prevent light spillage, incorporating the principles and mitigation measures contained in part A of the light obtrusion assessment, and in accordance with the exterior lighting strategy contained in part B of the light obtrusion assessment; and

schedule 2 paragraph 6 2 h (h)a detailed glint and glare assessment in respect of any part comprising solar energy production or canopies to support photovoltaic panels.

(3) The detailed design referred to in sub-paragraph (1)—

schedule 2 paragraph 6 3 a (a)is to be in accordance with the design principles;

schedule 2 paragraph 6 3 b (b)is to be within the limits shown on the works plans, subject to article 6(3) (limits of works);

schedule 2 paragraph 6 3 c (c)is to be within any relevant parameters set out in paragraph 7 (parameters of authorised development) of this Schedule, subject to paragraph 2(1)(g); and

schedule 2 paragraph 6 3 d (d)is not to give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.

(4) The authorised development must be carried out in accordance with the details approved under sub-paragraph (1).

(5) The undertaker must provide the relevant planning authority with—

schedule 2 paragraph 6 5 a (a)written notice of commencement of the part of the authorised development approved under sub-paragraph (1); and

schedule 2 paragraph 6 5 b (b)written notice of completion of that part of the authorised development as soon as reasonably practicable after that completion.