SCHEDULES
SCHEDULE 2REQUIREMENTS
PART 2REQUIREMENTS PERTAINING TO CONSTRUCTION
Phasing of authorised development
schedule 2 paragraph 5 5.—(1) The authorised development must not commence until a written scheme setting out the planned phases for construction of the authorised development has been submitted to and approved in writing by Luton Borough Council, in consultation with the specified authorities, Buckinghamshire Council and National Highways.
(2) The written scheme submitted under sub-paragraph (1) must be substantially in accordance with the phases shown on the scheme layout plans, except that this does not prevent the incremental delivery of parts of the authorised development within those phases nor require the delivery of a part within in a specific phase, provided this does not give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.
(3) The undertaker must undertake a review of, and make any necessary updates to, the written scheme no later than five years from the date the development is commenced, or sooner where a substantial change to the stages of construction is anticipated, and no later than every five years thereafter until construction of the authorised development is completed.
(4) The updated written scheme under sub-paragraph (3) must be submitted to and approved in writing by Luton Borough Council, in consultation with the specified authorities, Buckinghamshire Council and National Highways.
(5) The authorised development shall be carried out in accordance with the details approved unless otherwise agreed in writing by Luton Borough Council.
term written scheme (6) In this paragraph “written scheme” means a scheme which—
schedule 2 paragraph 5 6 a (a)identifies, with reference to the Schedule 1 works, the parts of the authorised development that are planned to be constructed within each phase;
schedule 2 paragraph 5 6 b (b)includes a layout plan showing the location of the works to be delivered in each phase; and
schedule 2 paragraph 5 6 c (c)includes an indicative construction programme for the next five-year period, and provides indicative timings for later phases.