SCHEDULE 2REQUIREMENTS

PART 2REQUIREMENTS PERTAINING TO CONSTRUCTION

Landscape and biodiversity management plan

schedule 2 paragraph 10 10.—(1) No part of the authorised development may commence, nor may powers under article 22 (felling, lopping and removal of trees, shrubs and hedgerows) be exercised in relation to that part, until for that part a landscape and biodiversity management plan has been submitted and approved in writing by the relevant planning authority.

(2) The landscape and biodiversity management plan approved under sub-paragraph (1) must be substantially in accordance with the outline landscape and biodiversity management plan.

(3) The authorised development must be carried out and maintained in accordance with the landscaping and biodiversity management plan referred to in sub-paragraph (1).

(4) Any tree or shrub planted as part of a landscaping scheme that, within the specified period after planting, is removed, uprooted, destroyed, dies or becomes in the opinion of the relevant planning authority, seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted unless otherwise agreed in writing with the relevant planning authority.

term specified period (5) In this paragraph, “specified period” means

schedule 2 paragraph 10 5 a (a)a period of 30 years in respect of the works implemented under Work No. 5b(01), Work No. 5c(01), Work No. 5c(02), Work No. 5d(01), Work No. 5d(02) and Work No. 5e in Schedule 1 to this Order; and

schedule 2 paragraph 10 5 b (b)A period of 5 years in all other respects,

or such other period as may be specified in accordance with the landscaping and biodiversity management plan.