ID badges: Hide | Show

SCHEDULES

SCHEDULE 15DEEMED MARINE LICENCE

PART 2LICENSABLE MARINE ACTIVITIES

schedule 15 paragraph 3 3.  Subject to the licence conditions in Part 4 of this licence, this licence authorises the undertaker to carry out any licensable marine activities under section 66(1) of the 2009 Act which involve the construction, alteration or improvement of any works in or over the sea or on or under the sea bed and which—

schedule 15 paragraph 3 a (a)form part of, or are related to, the authorised development; and

schedule 15 paragraph 3 b (b)are not exempt from requiring a marine licence by virtue of any provision made under section 74 of the 2009 Act.

schedule 15 paragraph 4 4.  The activities set out in this Part may be carried out by the undertaker as if licenced under the 2009 Act.

term authorised development schedule 15 paragraph 5 5.—(1) In this licence, “authorised development” means construction, alteration, improvement, maintenance, operation and decommissioning of those parts of each of the following works to the extent that such works constitute licensable marine activities—

schedule 15 paragraph 5 1 a (a)the construction and decommissioning of the drainage pipeline and outfall, during the construction phase, from the northern tunnel entrance compound which may include—

schedule 15 paragraph 5 1 a i (i)a buried pipe within the foreshore and a outfall structure at the discharge point that would terminate in a precast outfall or diffuser head on the subtidal riverbed slope and would be with a length of 400m and a maximum diameter of 1m; and

schedule 15 paragraph 5 1 a ii (ii)any works ancillary to these works;

schedule 15 paragraph 5 1 b (b)the construction of the operational discharge, during the tunnel operation, from the northern tunnel portal site which may include—

schedule 15 paragraph 5 1 b i (i)an outfall structure located at mean high water including the installation of a flap valve type outfall structure; and

schedule 15 paragraph 5 1 b ii (ii)any works ancillary to these works;

schedule 15 paragraph 5 1 c (c)the construction of the water inlet at Coalhouse Point which may include—

schedule 15 paragraph 5 1 c i (i)a water inlet with self-regulating valve structure below mean high water in a new section of flood defence wall;

schedule 15 paragraph 5 1 c ii (ii)a piled coffer dam (10m x 15m) within a defined working area 50m x 35m on the intertidal zone; and

schedule 15 paragraph 5 1 c iii (iii)any works ancillary to these works.

(2) The grid coordinates for the area of the river Thames within which the undertaker may carry out licensed activities specified under paragraph (1) are located at—

schedule 15 paragraph 5 2 a (a)in relation to the drainage pipeline and outfall referred to at paragraph 5(1)(a) during the construction phase, from the northern tunnel entrance compound—

StructurePointETRS89 (decimal degrees)
LatitudeLongitude
OutfallCentre51.4541110.413873
Discharge pipeline working areaNorth west51.4559230.412713
North east51.4560740.41339
South west51.4522630.415053
South east51.4521750.414348

schedule 15 paragraph 5 2 b (b)in relation to the operational outfall referred to at paragraph 5(1)(b) during the tunnel operation, from the northern tunnel portal site—

StructurePointETRS89 (decimal degrees)
LatitudeLongitude
OutfallNorth west51.455920.414477
North east51.456010.414733
South west51.455850.414527
South east51.455930.414782

schedule 15 paragraph 5 2 c (c)in relation to the water inlet at Coalhouse Point referred to at paragraph 5(1)(c)—

StructurePointETRS89 (decimal degrees)
LatitudeLongitude
Water inletNorth west51.458690.426321
North east51.4588510.426999
South west51.4583870.426455
South east51.4585530.427135