SCHEDULES
SCHEDULE 15DEEMED MARINE LICENCE
PART 4CONDITIONS
Licensable marine activity at Coalhouse Point
schedule 15 paragraph 19 19.—(1) The licensable marine activities referred to at paragraph 5(1)(c) must not commence until a detailed design plan has been submitted to and approved in writing by the MMO. The detailed design plan must include—
schedule 15 paragraph 19 1 a (a)the specifications and dimensions of the water inlet;
schedule 15 paragraph 19 1 b (b)the proposed location, including grid co-ordinates;
schedule 15 paragraph 19 1 c (c)a construction programme including details of—
schedule 15 paragraph 19 1 c i (i)the proposed construction commencement date; and
schedule 15 paragraph 19 1 c ii (ii)proposed timings for mobilisation of plant, delivery of materials and construction; and
schedule 15 paragraph 19 1 d (d)a construction method statement in accordance with the construction methods assessed in the environmental statement.