SCHEDULE 15DEEMED MARINE LICENCE

PART 4CONDITIONS

Licensable marine activity at Coalhouse Point

schedule 15 paragraph 19 19.—(1) The licensable marine activities referred to at paragraph 5(1)(c) must not commence until a detailed design plan has been submitted to and approved in writing by the MMO. The detailed design plan must include—

schedule 15 paragraph 19 1 a (a)the specifications and dimensions of the water inlet;

schedule 15 paragraph 19 1 b (b)the proposed location, including grid co-ordinates;

schedule 15 paragraph 19 1 c (c)a construction programme including details of—

schedule 15 paragraph 19 1 c i (i)the proposed construction commencement date; and

schedule 15 paragraph 19 1 c ii (ii)proposed timings for mobilisation of plant, delivery of materials and construction; and

schedule 15 paragraph 19 1 d (d)a construction method statement in accordance with the construction methods assessed in the environmental statement.