SCHEDULE 14PROTECTIVE PROVISIONS

PART 8FOR THE PROTECTION OF THE PORT OF LONDON AUTHORITY

Interpretation

schedule 14 paragraph 97 97.  In this Schedule—

term begin begin” means beginning to carry out any material operation (as defined in section 56(4) (time when development begun) of the 1990 Act) forming part of the authorised development including preliminary works (as defined in Schedule 2 of this Order) including any ground investigations in the river Thames;

term construction construction” includes execution, placing, altering, replacing, relaying, removal, renewal and works of maintenance within a maintenance period defined in article 36 (temporary use of land for maintaining the authorised development) and, in its application to a specified work which includes or comprises any operation, means the carrying out of that operation, and “construct” and “constructed” are to be construed accordingly;

term harbourmaster term harbour master Harbour Master” has the same meaning as “harbourmaster” in section 2(1) of the 1968 Act;

term plans plans” includes navigational risk assessments, plans, sections, elevations, drawings, specifications, programmes, construction methods and descriptions including, where applicable, such relevant hydraulic information about the river Thames as may be reasonably requested by the PLA;

term lower thames crossing ground investigations navigational risk assessment term preliminary navigational risk assessment preliminary navigational risk assessment” means the document of that description listed in Schedule 16 (documents to be certified) and certified by the Secretary of State as the preliminary navigational risk assessment and, in connection with any ground investigations in the river Thames, means the “Lower Thames Crossing Ground Investigations Navigational Risk Assessment” (which forms Appendix F of the preliminary navigational risk assessment);

term specified function specified function” means any function of the undertaker under this Order (except any function under article 25 (compulsory acquisition of land), article 28 (compulsory acquisition of rights and imposition of restrictive covenants), article 33 (acquisition of subsoil or airspace only)) the exercise of which may affect the river Thames or any function of the PLA;

term specified work specified work” means any part of the authorised development (which for this purpose includes the removal of any part of the authorised development), which—

(a)

is, may be, or takes place in, on, under or over the surface of land below the level of mean high water forming part of the river Thames; or

(b)

may affect the river Thames or any function of the PLA,

including any projection over the river Thames by any authorised work or any plant or machinery or any dredging (as defined in the 1968 Act) in the river Thames;

term temporary outfall temporary outfall” means the temporary outfall in the river Thames referenced in paragraph 5(2)(a) of Schedule 15 (deemed marine licence) to this Order; and

term tunnelling works tunnelling works” means so much of Work No. 4A as is carried out wholly under the bed of the River Thames.