ID badges: Hide | Show

PART 7MISCELLANEOUS AND GENERAL

Planning permission, etc.

article 56 56.—(1) If planning permission is granted under the powers conferred by the 1990 Act for development any part of which is within the Order limits following the coming into force of this Order that is—

article 56 1 a (a)not itself a nationally significant infrastructure project under the 2008 Act or part of such a project; or

article 56 1 b (b)required to complete or enable the use or operation of any part of the development authorised by this Order,

then the construction, maintenance, use or operation of that development under the terms of the planning permission does not constitute a breach of the terms of this Order.

(2) Development consent granted by this Order is to be deemed as specific planning permission for the purposes of section 264(3) (cases in which land is not to be treated as operational land for the purposes of that Act) of the 1990 Act.

(3) To the extent any development carried out or used pursuant to a planning permission granted under section 57(1) (requirement of planning permission) of the 1990 Act or compliance with any conditions of that permission is inconsistent with the exercise of any power, right or obligation under this Order or the authorised development—

article 56 3 a (a)that inconsistency is to be disregarded for the purposes of establishing whether any development which is the subject matter of that planning permission is capable of physical implementation; and

article 56 3 b (b)in respect of that inconsistency, no enforcement action under the 1990 Act may be taken in relation to development carried out or used pursuant to that planning permission, or compliance with any conditions of that permission, whether inside or outside the Order limits.

(4) Any development or any part of a development within the Order limits which is constructed or used under the authority of a permission granted under section 57 of the 1990 Act including permissions falling under paragraphs (1) or (3), is deemed not to be a breach of, or inconsistent with, this Order and does not prevent the authorised development being carried out or used or any other power or right under this Order being exercised.

(5) Any works carried out under this Order are deemed to be immediately required for the purpose of carrying out development authorised by planning permission granted under the 1990 Act for the purposes of section 9 (requirement of licence for felling)(2) of the Forestry Act 1967.

term enforcement action (6) In paragraph (3), “enforcement action” means any enforcement action provided for under Part 7 of the 1990 Act.

(1)

Section 57 was amended by paragraphs 34 and 35 of Schedule 2 to the Planning Act 2008, paragraphs 1 and 3 of Schedule 2 to the Localism Act 2011 (c. 20) and paragraphs 2 and 4 of Part 2 of Schedule 4 to the Infrastructure Act 2015.

(2)

1967 c. 10. Relevant amendments to section 9 have been made by section 4 of, and Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11).