ID badges: Hide | Show

SCHEDULES

SCHEDULE 2REQUIREMENTS

PART 1REQUIREMENTS

Code of construction practice

schedule 2 paragraph 8 8.—(1) Each phase must be undertaken in accordance with the code of construction practice in so far as it relates to the works proposed in the relevant phase.

(2) Where a document referred to in the code of construction practice is submitted for approval to the relevant planning authority under a requirement specified in this Part of this Schedule the submitted document must accord with details specified in the code of construction practice for that document in so far as those details relate to works proposed in the relevant phase.