SCHEDULES
SCHEDULE 2REQUIREMENTS
PART 1REQUIREMENTS
Temporary stopping up of public rights of way
schedule 2 paragraph 26 26. No phase of the authorised development which includes the temporary stopping up of a public right of way is to commence until the undertaker has provided the relevant highway authority with a programme of stopping up for those public rights of way to be temporarily stopped up in that phase.