SCHEDULES
SCHEDULE 2REQUIREMENTS
PART 1REQUIREMENTS
Outfall
schedule 2 paragraph 10 10.—(1) No phase of the authorised development comprising works within the area of Work No. 32 as shown on the works plans is to commence until a detailed construction outfall management and monitoring plan relating to the construction of works within that area has been submitted to and approved by the relevant planning authority following consultation by the relevant planning authority with Natural England, the Environment Agency and the relevant navigation authority.
(2) The detailed construction outfall management and monitoring plan submitted for approval must accord with the measures set out in the outline outfall management and monitoring plan relating to construction and must include—
schedule 2 paragraph 10 2 a (a)details of ditch habitat creation, monitoring and maintenance measures;
schedule 2 paragraph 10 2 b (b)details of any proposed restrictions on navigation on the river Cam during construction works;
schedule 2 paragraph 10 2 c (c)details of proposed communication of restrictions to river users and the relevant navigation authority; and
schedule 2 paragraph 10 2 d (d)details of public footpath diversions during construction and proposed reinstatement methods.
(3) The detailed construction outfall management and monitoring plan may be revised from time to time in accordance with requirement 6 following consultation with the Environment Agency, Natural England and the relevant navigation authority to reflect the requirements of any environmental permit, protected species licence or land drainage consent.
(4) Any works within the area of Work No. 32 must be carried out in accordance with the approved detailed construction outfall management and monitoring plan.
(5) The outfall forming part of Work No. 32 must not be brought into operational use until a detailed operational outfall management and monitoring plan has been submitted to and approved by the relevant planning authority following consultation by the relevant planning authority with Natural England, the Environment Agency and the relevant navigation authority.
(6) The detailed operational outfall management and monitoring plan submitted for approval must accord with the measures set out in the outline outfall management and monitoring plan relating to the operation of the outfall and must include—
schedule 2 paragraph 10 6 a (a)details of proposal for monitoring scour and bank erosion;
schedule 2 paragraph 10 6 b (b)potential adaptive management measures in the event of erosion arising from outfall operation;
schedule 2 paragraph 10 6 c (c)the circumstances in which adaptive management measures will be deployed; and
schedule 2 paragraph 10 6 d (d)details of ditch monitoring and maintenance measures.
(7) The detailed operational outfall management and monitoring plan may be revised from time to time in accordance with requirement 6 following consultation with the Environment Agency, Natural England and the relevant navigation authority to reflect the requirements of any environmental permit, protected species licence or land drainage consent.
(8) The detailed operational outfall management and monitoring plan must be implemented as approved upon commencement of operation of the outfall.