SCHEDULES
SCHEDULE 15PROTECTIVE PROVISIONS
PART 6FOR THE PROTECTION OF LOCAL HIGHWAY AUTHORITIES
Interpretation
schedule 15 paragraph 76 76.—(1) Where the terms defined in article 2 (interpretation) of this Order are inconsistent with sub-paragraph (2), the latter prevail.
(2) In this Part of this Schedule—
term agreement fee “agreement fee” means a sum equal to eight and a half per cent (8.5%) of the works estimate in respect of the local highway authority’s technical approval, administration and inspection costs for keeping the specified works under observation and inspection during the period of construction from when any specified works begin to when the provisional certificate of completion is issued and undertaking the pre-maintenance inspection pursuant to paragraph 88(1) of this Part of this Schedule and final inspection pursuant to paragraph 90(6) of this Part of this Schedule;
term approved drawings “approved drawings” means those plans drawings, calculations and diagrams required to demonstrate that the specified works can reasonably be constructed within the local highway which shall be substantially in accordance with the highways plans and approved pursuant to this Part of this Schedule;
term approved programme and method statement and traffic management proposals “approved programme and method statement and traffic management proposals” means respectively the detailed programme of works and the method statement and traffic management proposals as approved by the local highway authority as set out in paragraph 81 of this Part of this Schedule and reference to any one of them and the term “the programme” must be construed accordingly;
term asset management fee “asset management fee” means the sum of £150.00 towards amending the local highway authority’s legal records;
term asset planning fee “asset planning fee” means the sum of £150.00 towards adding and amending the local highway authority’s highway asset inventory;
term cash deposit “cash deposit” means a sum equivalent to the works sum;
term cdm regulations “CDM Regulations” means The Construction (Design and Management) Regulations 2015;
term cessation of works notice “cessation of works notice” means a notice served by the local highway authority on the undertaker requiring the undertaker to forthwith cease carrying out the specified works specified in the notice;
term commencement notice “commencement notice” means at least twenty (20) working days’ notice to be given by the undertaker to the local highway authority of the undertaker’s intention to commence the specified works on the local highway;
term commuted sum “commuted sum” means a payment to the local highway authority calculated in accordance with the formulas pursuant to Cambridgeshire County Council’s ‘Highways Commuted Sums’ policy dated 1 April 2023;
term conditions of contract “conditions of contract” means the contract for the specified works which must be let by the undertaker using the New Engineering Contract version 3 2013 (NEC3) or version 4 2017 (NEC4) as amended in 2023 or such other contract as may be approved by the local highway authority;
term conditions survey “conditions survey” means a survey of the surface features of the existing local highway recording any existing defects, damage or missing elements and the required record shall include photographs and a location measured from the centre line of the proposed works noting the cardinal direction or intermediate directions for the side of the local highway;
term contractor “contractor” means a suitably qualified contractor nominated by the undertaker and approved by the local highway authority (such approval not to be unreasonably withheld or delayed);
term defects “defects” means any damage or defects to the specified works identified by the local highway authority as part of the pre-maintenance inspection pursuant to paragraph 88(1) of this Part of this Schedule and the final inspection pursuant to 90(6) of this Part of this Schedule;
term final certificate “final certificate” means the certificate issued by the local highway authority at the end of the maintenance period and following the stage 3 safety audit (or the stage 4 safety audit, if necessary, as the case may be) signifying the specified works are satisfactory and any defects have been remedied and otherwise made good to the satisfaction of the local highway authority;
term health and safety file “health and safety file” means the health and safety documentation required under the CDM Regulations prepared by the undertaker and submitted to the local highway authority;
“designers response” as described in GG119 of the Design Manual for Roads and Bridges;
term housing estate road construction specification “Housing Estate Road Construction Specification” means the specification within Cambridgeshire County Council’s Development Management – General Principals of Development policy document published by the local highway authority on 7 March 2023;
term local highway “local highway” means any public, vehicular highway, way, route, footpath, cycle route, footway, carriageway, bridleway, byway-open-to-all-traffic which vests or is intended at the completion of specified works to vest in or be otherwise maintainable by the local highway authority at public expense;
term local highway authority “local highway authority” means the highway authority with responsibility for the relevant local highway pursuant to the 1980 Act;
term maintenance period “maintenance period” means the period of not less than 12 months from the date of the provisional certificate of completion;
term overseeing organisation “overseeing organisation” has the meaning as described in GG119 of the Design Manual for Roads and Bridges;
term post construction inventory “post-construction inventory” means an inventory of new highway assets listing the number and area of each element of the new assets within the specified works as specified by the local highway authority;
term provisional certificate of completion “provisional certificate of completion” means the certificate issued by the local highway authority confirming the specified works have been completed and have been found to be satisfactory to the local highway authority;
term specification “specification” means the Housing Estate Road Construction Specification and where applicable the ‘Design Manual for Roads and Bridges’ and any other such specifications as reasonably required by the local highway authority and as may be amended from time to time;
term specified works “specified works” means any highway works and any street works carried out within the local highway as part of the authorised development and includes any part of the specified works (as the case may be);
term stage 2 safety audit “stage 2 safety audit” means the audit undertaken of the detailed design of the specified works prior to the commencement of the specified works. The audit shall be undertaken in compliance with the requirements of GG119 of the ‘Design Manual for Roads and Bridges’;
term stage 3 safety audit “stage 3 safety audit” means the audit undertaken following completion of the specified works in compliance with the requirements of GG119 of the ‘Design Manual for Roads and Bridges’;
term stage 4 safety audit “stage 4 safety audit” means the safety audit undertaken in compliance with the requirements of GG119 of the ‘Design Manual for Roads and Bridges’ at the discretion of the local highway authority following expiration of the maintenance period to assess the specified works in order to determine whether any remedial works are required prior to issue of the final certificate;
term statutory undertaker highways “statutory undertaker (highways)” means a statutory undertaker as defined in section 329(1)(1) (further provision as to interpretation) of the 1980 Act and all those bodies deemed to be statutory undertakers for the purposes of the 1980 Act and all those undertakers licensed in accordance with the 1991 Act;
term street lighting design review “street lighting design review” means a review of street lighting comprised in the specified works, such review to include layout design and specification;
term technical approval “technical approval” means approval granted to the undertaker by the local highway authority in connection with each of the specified works at a specific specified works location enabling these to progress to on site operations;
term third party notice information “third party notice information” means—
a brief description of the specified works emphasising any changes to the appearance of the streetscape (e.g. removal of grass verges or significant changed in materials used);
planned start date;
contract period or planned completion date;
name and address of contractor carrying out the specified works;
details of the person responsible for supervision of the specified works including an address and telephone number to contact should a query arise;
details of emergency contact(s) for the specified works which are to be available twenty four hours a day seven days a week for each area of specified works until the final certificate is issued and the contact details must include a telephone number and email address; and
where further details of the proposed specified works may be viewed;
term third party notices “third party notices” means at least 20 working days’ notice to be given by the undertaker to—
the Parish, City or Town Council for the area in which the works are located; and
the owner and occupier of every premises adjoining the part of the local highway on which the specified works are to be carried out by letter addressed to “the owner/occupier of [address]” and sent by first class post or delivered to each premises
containing the third party notice information;
term works estimate “works estimate” means in relation to each part of the specified works the sum specified in the bill of quantities for the relevant part of the specified works in accordance with paragraph 102(5) of this Part of this Schedule;
term works sum “works sum” means a sum equivalent to the works estimate plus 10% (contingency).