SCHEDULE 15PROTECTIVE PROVISIONS

PART 3FOR THE PROTECTION OF CADENT GAS LIMITED AS GAS UNDERTAKER

Protective works to buildings

schedule 15 paragraph 23 23.—(1) The undertaker, in the case of the powers conferred by article 20 (protective works to buildings and structures), must exercise those powers so as not to obstruct or render less convenient the access to any apparatus without the written consent of Cadent and, if by reason of the exercise of those powers any damage to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal or abandonment) or property of Cadent or any interruption in the supply of gas by Cadent, as the case may be, is caused, the undertaker must bear and pay on demand the cost reasonably incurred by Cadent in making good such damage or restoring the supply; and subject to sub-paragraph (2), will—

schedule 15 paragraph 23 1 a (a)pay compensation to Cadent for any loss sustained by it; and

schedule 15 paragraph 23 1 b (b)indemnify Cadent against all claims, demands, proceedings, costs, damages and expenses which may be made or taken against or recovered from or incurred by Cadent, by reason of any such damage or interruption.

(2) Nothing in this paragraph 23 imposes any liability on the undertaker with respect to any damage or interruption to the extent that such damage or interruption is attributable to the act, neglect or default of Cadent or its contractors or workmen; and Cadent will give to the undertaker reasonable notice of any claim or demand as aforesaid and no settlement or compromise thereof will be made by Cadent, save in respect of any payment required under a statutory compensation scheme, without first consulting the undertaker and giving the undertaker an opportunity to make representations as to the claim or demand.