SCHEDULE 15PROTECTIVE PROVISIONS
PART 7FOR THE PROTECTION OF THE RELEVANT NAVIGATION AUTHORITY
Details for approval
schedule 15 paragraph 110 110.—(1) The undertaker must, at the same time as the provision of the plans pursuant to paragraph 109(1)(a) of this Part of this Schedule, provide for the approval of the relevant navigation authority—
schedule 15 paragraph 110 1 a (a)details of the extent of any temporary suspension of rights of navigation required pursuant to article 44(3) (rights on the river Cam) in order to carry out the relevant river work and the undertaker must not interfere with any rights of navigation pursuant to article 44(3) except in accordance with this paragraph 110; and
schedule 15 paragraph 110 1 b (b)details of any temporary or permanent signage required in connection with the river work.
(2) The relevant navigation authority must respond in writing within 42 days of the request for approval under sub-paragraph (1) to either give approval to the details as submitted or suggest amendments to the details provided, but any such amendment must not materially affect or delay the efficient delivery of the relevant river work and must be suggested only where the relevant navigation authority considers such amendment necessary (acting reasonably) in accordance with its functions and duties in its capacity as the relevant navigation authority.
(3) If the relevant navigation authority provides pursuant to sub-paragraph (2) any suggested amendments to the details provided, the undertaker must within 14 days confirm whether those amendments are accepted and in the event the undertaker agrees to the amendments, the undertaker must carry out the relevant river work in accordance with those amendments. In the event the undertaker does not agree to the amendment, the dispute may be referred to and settled by arbitration in accordance with article 52 (arbitration) and the relevant river work is to be undertaken in accordance with the terms of the final determination.
(4) If the relevant navigation authority fails to respond to the undertaker’s request for approval pursuant to this paragraph 110 within 42 days, approval is deemed to have been given.
(5) The undertaker must pay the relevant navigation authority a sum equal to the whole of any costs and expenses reasonably and properly incurred by the relevant navigation authority in relation to any approvals sought under this paragraph 110 within 30 days of written evidence of such costs and expenses.