PART 6FOR THE PROTECTION OF LOCAL HIGHWAY AUTHORITIES
Documents submitted for approval
schedule 15 paragraph 102 102.—(1) Any documents submitted by the undertaker to the local highway authority shall conform to the following requirements—
schedule 15 paragraph 102 1 a (a)In respect of construction details – the Housing Estate Road Construction Specification;
schedule 15 paragraph 102 1 b (b)Where required by the local highway authority – the design manual for roads and bridges and the accompanying suite of documents;
(2) Any and all copyright requirements of the undertaker and its representatives shall be waived in respect of the normal requirements of the local highway authority and such permission shall be provided in writing.
(3) If deemed necessary by the local highway authority for each part of the specified works the undertaker shall provide all documentation required under GG119 of the Design Manual for Roads and Bridges to undertake a stage 2 safety audit.
(4) Where a stage 2 safety audit has been required by the local highway authority no part of that specified works shall be undertaken until the stage 2 safety audit has been completed to the satisfaction of the overseeing organisation.
(5) Prior to the specified works commencing the undertaker will submit to the local highway authority for approval a provisionally priced bill of quantities for the specified works and any land to be dedicated as public highway as part of the specified works and such bill of quantities must—
schedule 15 paragraph 102 5 a (a)comply with the layout and requirements of the specified works; and
schedule 15 paragraph 102 5 b (b)include elements for traffic management
and this figure will be the works estimate.