SCHEDULE 1AUTHORISED DEVELOPMENT

Work No. 26 – DIVERSION OF RIVERSIDE TUNNEL

Works to divert the existing riverside sewer to connect to Work No. 18 comprising—

schedule 1 paragraph wrapper26 a (a)temporary diversion works including a temporary shaft/pit and temporary overground pipes, underground pipework to connect the Riverside sewer to Work No. 18;

schedule 1 paragraph wrapper26 b (b)installation of temporary pumps and power supply including generators and fuel storage;

schedule 1 paragraph wrapper26 c (c)removal of temporary works; and

schedule 1 paragraph wrapper26 d (d)decommissioning works to the redundant sewer.