SCHEDULES
SCHEDULE 1AUTHORISED DEVELOPMENT
Work No. 13 – TERTIARY TREATMENT
Tertiary treatment works including—
schedule 1 paragraph wrapper13 a (a)filtration plant;
schedule 1 paragraph wrapper13 b (b)wash-water pump sets;
schedule 1 paragraph wrapper13 c (c)airlift pumps;
schedule 1 paragraph wrapper13 d (d)sand washing system;
schedule 1 paragraph wrapper13 e (e)backwash pumps;
schedule 1 paragraph wrapper13 f (f)chemical storage and ferric dosing plant; and
schedule 1 paragraph wrapper13 g (g)connections to Work Nos. 4, 6, 8, 11, and 12.