SCHEDULES
Article 3
SCHEDULE 1AUTHORISED DEVELOPMENT
Development which, in accordance with a direction made by the Secretary of State under section 35(1) (directions in relation to projects of national significance) of the 2008 Act on 18 January 2021, is development for which development consent is required in the County of Cambridgeshire, the District of South Cambridgeshire and the City of Cambridge, being a waste water treatment plant together with associated development within the meaning of section 115(1)(b) (development for which development consent may be granted) of the 2008 Act comprising—
Work No. 1 – HIGHWAY WORKS
Highway works the general arrangement of which is shown on sheet 1 of the highways plans including—
schedule 1 paragraph wrapper1 a (a)reconfiguration of the existing signalised junction of B1047 Horningsea Road and A14 Junction 34 eastbound slip road to provide a signalised four-arm junction facilitating access to Work No. 2;
schedule 1 paragraph wrapper1 b (b)widening of and improvements to the existing footway/cycleway on the western side of the B1047 Horningsea Road and Horningsea Road between the westbound on-slip at A14 Junction 34 and Low Fen Drove Way including the provision of a verge between the footway/cycleway and the main carriageway;
schedule 1 paragraph wrapper1 c (c)provision of a new central island on Horningsea Road to facilitate pedestrian and cyclist crossing to new footpaths and cycleways to be provided as part of Work No. 23 and the new footway/cycleway to be provided at (d);
schedule 1 paragraph wrapper1 d (d)a new footway/cycleway on the eastern side of Horningsea Road between Low Fen Drove Way and the new central island to be provided at (c) and connecting to new footpaths and cycleways to be provided as part of Work No. 23;
schedule 1 paragraph wrapper1 e (e)replacement of the parapet on the A14 overbridge on the B1047 Horningsea Road and associated highway layout alterations;
schedule 1 paragraph wrapper1 f (f)improvements to the existing pedestrian and cycle crossings at the junction of the A14 Junction 34 on and off slips on the B1047 Horningsea Road;
schedule 1 paragraph wrapper1 g (g)alterations to the B1047 Horningsea Road and Horningsea Road;
schedule 1 paragraph wrapper1 h (h)street lighting, signage and associated electrical equipment;
schedule 1 paragraph wrapper1 i (i)reconfiguration of kerb lines; and
schedule 1 paragraph wrapper1 j (j)connections to Work No. 2.
Work No. 2 – PERMANENT ACCESS ROAD
A new two-lane road access to the waste water treatment plant from the reconfigured A14 Junction 34/B1047 Horningsea Road junction the general arrangement of which is shown on sheet 1 of the highways plans including—
schedule 1 paragraph wrapper2 a (a)landscaping;
schedule 1 paragraph wrapper2 b (b)drainage;
schedule 1 paragraph wrapper2 c (c)a weighbridge;
schedule 1 paragraph wrapper2 d (d)automatic number plate recognition cameras;
schedule 1 paragraph wrapper2 e (e)signage;
schedule 1 paragraph wrapper2 f (f)street lighting at the junction with Work No. 1; and
schedule 1 paragraph wrapper2 g (g)connections to Work No. 1 and Work No. 3 and to the access and circulation roads to be constructed within the inner boundary of Work No. 15.
Work No. 3 –VISITOR PARKING
Visitor parking, cycle storage including landscaping, lighting, pathways and electric vehicle charging points and connections to Work No. 2.
Work No. 4 – INLET WORKS & PRELIMINARY TREATMENT
Inlet works structure to receive flows from Work No. 8, Work No. 16 and Work No. 35 and imported liquors including—
schedule 1 paragraph wrapper4 a (a)two screenings handling plants;
schedule 1 paragraph wrapper4 b (b)screen channel;
schedule 1 paragraph wrapper4 c (c)grit removal chambers;
schedule 1 paragraph wrapper4 d (d)flow measurement channel;
schedule 1 paragraph wrapper4 e (e)grit handling plant;
schedule 1 paragraph wrapper4 f (f)two odour control units and exhaust stacks;
schedule 1 paragraph wrapper4 g (g)skip storage area;
schedule 1 paragraph wrapper4 h (h)cess and septic discharge point; and
schedule 1 paragraph wrapper4 i (i)connections to Work No. 6, Work No. 8, Work No. 13, Work No. 16 and Work No. 35.
Work No. 5 – ELECTRICAL SUPPLY AND POWER GENERATION
Electricity substations, ring main units, transformers, high-voltage kiosk, low voltage switch board, low voltage kiosk, stand-by generators and fuel storage.
Work No. 6 – PRIMARY TREATMENT & CHEMICAL DOSING
Primary treatment works including—
schedule 1 paragraph wrapper6 a (a)chemical storage and ferric dosing plant;
schedule 1 paragraph wrapper6 b (b)up to 6 primary settlement tanks including sludge management system;
schedule 1 paragraph wrapper6 c (c)sludge return pumps;
schedule 1 paragraph wrapper6 d (d)sludge transfer pumping station;
schedule 1 paragraph wrapper6 e (e)distribution chamber; and
schedule 1 paragraph wrapper6 f (f)connections to Work Nos. 4, 8, 10, 11 and 13.
Work No. 7 – WORKSHOP & PARKING
A workshop building and parking including—
schedule 1 paragraph wrapper7 a (a)workshop building;
schedule 1 paragraph wrapper7 b (b)innovation area;
schedule 1 paragraph wrapper7 c (c)welfare facilities;
schedule 1 paragraph wrapper7 d (d)liquefied natural gas (LNG) storage and filling point;
schedule 1 paragraph wrapper7 e (e)vehicle parking including HGV parking;
schedule 1 paragraph wrapper7 f (f)electric vehicle charging points; and
schedule 1 paragraph wrapper7 g (g)rooftop solar photovoltaic panels.
Work No. 8 – SLUDGE TREATMENT CENTRE
A sludge treatment centre comprising—
schedule 1 paragraph wrapper8 a (a)sludge reception facilities for imported primary settled sludge and surplus activated sludge;
schedule 1 paragraph wrapper8 b (b)up to 2 imported and indigenous primary sludge tanks;
schedule 1 paragraph wrapper8 c (c)up to 3 unthickened sludge tanks;
schedule 1 paragraph wrapper8 d (d)screens;
schedule 1 paragraph wrapper8 e (e)up to 2 odour control units with vent stacks;
schedule 1 paragraph wrapper8 f (f)thickening building including a sludge blending tank;
schedule 1 paragraph wrapper8 g (g)up to two anaerobic sludge digesters;
schedule 1 paragraph wrapper8 h (h)up to 2 post digestion storage tanks and vacuum de-gassing units;
schedule 1 paragraph wrapper8 i (i)a heating, pasteurisation and hydrolysis process heating tank;
schedule 1 paragraph wrapper8 j (j)up to 2 heating, pasteurisation and hydrolysis process pasteurisation tanks;
schedule 1 paragraph wrapper8 k (k)a heating, pasteurisation and hydrolysis process hydrolysis tank;
schedule 1 paragraph wrapper8 l (l)up to 2 dewatering centrifuges/volutes;
schedule 1 paragraph wrapper8 m (m)cake storage barn and silo area;
schedule 1 paragraph wrapper8 n (n)either—
schedule 1 paragraph wrapper8 n i (i)a liquor treatment plant including a reactor, a stilling tank and a settlement tank; and/or
schedule 1 paragraph wrapper8 n ii (ii)a nutrient recovery plant including three stripping/scrubbing columns and a feed pumping station; and/or
schedule 1 paragraph wrapper8 n iii (iii)a hybrid liquor treatment plant and nutrient recovery plant;
schedule 1 paragraph wrapper8 o (o)biogas handling equipment including up to 2 gas holders and a flare stack;
schedule 1 paragraph wrapper8 p (p)boiler building and boiler stack;
schedule 1 paragraph wrapper8 q (q)final effluent heat recovery and treatment plant;
schedule 1 paragraph wrapper8 r (r)chemical storage and dosing plant;
schedule 1 paragraph wrapper8 s (s)aviation obstruction lighting; and
schedule 1 paragraph wrapper8 t (t)connections to Work Nos. 4, 6, 9, 10, 11 and 13.
Work No. 9 – GAS TO GRID OR COMBINED HEAT AND POWER (CHP)
A gas-to-grid injection unit including propane storage or a CHP engine including connections to Work No. 8 and connections to the gas and/or electricity networks.
Work No. 10 – SECONDARY TREATMENT MEMBRANE AERATED BIOFILM REACTOR (MABR)
Secondary treatment works including—
schedule 1 paragraph wrapper10 a (a)up to 4 activated sludge process tanks;
schedule 1 paragraph wrapper10 b (b)mixing and conditioning tank;
schedule 1 paragraph wrapper10 c (c)building to house mechanical blower system;
schedule 1 paragraph wrapper10 d (d)submerged air distribution pipework;
schedule 1 paragraph wrapper10 e (e)mixing and conditioning chamber;
schedule 1 paragraph wrapper10 f (f)interstage pumping station; and
schedule 1 paragraph wrapper10 g (g)connections to Work No. 6 and Work No. 11.
Work No. 11 – SECONDARY TREATMENT (SETTLEMENT)
Final settlement including—
schedule 1 paragraph wrapper11 a (a)up to 8 final settlement tanks including sludge management system;
schedule 1 paragraph wrapper11 b (b)return activated sludge pumps including chambers;
schedule 1 paragraph wrapper11 c (c)surplus activated sludge pumps including chambers;
schedule 1 paragraph wrapper11 d (d)pumping station;
schedule 1 paragraph wrapper11 e (e)chemical storage and ferric dosing plant;
schedule 1 paragraph wrapper11 f (f)distribution chamber; and
schedule 1 paragraph wrapper11 g (g)connections to Work Nos. 6, 8, 10 and 13.
Work No. 12 – TREATED WATER COLLECTION CHAMBER
Treated water collection chamber and connections to Work No. 13, Work No. 14 and Work No. 31.
Work No. 13 – TERTIARY TREATMENT
Tertiary treatment works including—
schedule 1 paragraph wrapper13 a (a)filtration plant;
schedule 1 paragraph wrapper13 b (b)wash-water pump sets;
schedule 1 paragraph wrapper13 c (c)airlift pumps;
schedule 1 paragraph wrapper13 d (d)sand washing system;
schedule 1 paragraph wrapper13 e (e)backwash pumps;
schedule 1 paragraph wrapper13 f (f)chemical storage and ferric dosing plant; and
schedule 1 paragraph wrapper13 g (g)connections to Work Nos. 4, 6, 8, 11, and 12.
Work No. 14 – STORMWATER MANAGEMENT
Storm management plant for stormwater storage and treatment including—
schedule 1 paragraph wrapper14 a (a)pumping station;
schedule 1 paragraph wrapper14 b (b)storm tanks;
schedule 1 paragraph wrapper14 c (c)stormwater storage facility;
schedule 1 paragraph wrapper14 d (d)discharge overflow pipework;
schedule 1 paragraph wrapper14 e (e)screens; and
schedule 1 paragraph wrapper14 f (f)connections to Work No. 16 and Work No. 12.
Work No. 15 – EARTH BUND & SOLAR PHOTOVOLTAIC PANELS (PV)
Landscaping and earthworks including—
schedule 1 paragraph wrapper15 a (a)solar photovoltaic panels and associated mounting structures, inverters, transformers and cabling;
schedule 1 paragraph wrapper15 b (b)security fencing; and
schedule 1 paragraph wrapper15 c (c)closed circuit television cameras.
Work No. 16 – TERMINAL PUMPING STATION
A terminal pumping station including a shaft and including the following—
schedule 1 paragraph wrapper16 a (a)dry weather flow pumps;
schedule 1 paragraph wrapper16 b (b)storm pumps;
schedule 1 paragraph wrapper16 c (c)valve chamber and control building;
schedule 1 paragraph wrapper16 d (d)dewatering; and
schedule 1 paragraph wrapper16 e (e)connections to Work Nos. 4, 14, 27 and 35.
Work No. 17 – EXISTING RISING AND GRAVITY MAIN DIVERSIONS
Works to divert existing rising and gravity mains to Work No.18 comprising—
schedule 1 paragraph wrapper17 a (a)cuttings into existing mains in under or adjacent to Cowley Road;
schedule 1 paragraph wrapper17 b (b)connections from existing mains to new 750mm gravity main;
schedule 1 paragraph wrapper17 c (c)provision of manholes;
schedule 1 paragraph wrapper17 d (d)installation of new 750mm gravity main;
schedule 1 paragraph wrapper17 e (e)associated diversion works for existing utilities including the Fen Ditton rising main; and
schedule 1 paragraph wrapper17 f (f)decommissioning works to redundant mains.
Work No. 18 – INTERCEPTION AND FIRST CONSTRUCTION SHAFT
Interception shaft to intercept incoming waste water flows from the existing Riverside tunnel and receive flows from a new 750mm gravity main within Work No. 17 with an internal diameter of up to 12.5 metres and with a depth of up to 20 metres including—
schedule 1 paragraph wrapper18 a (a)ventilation stack extending up to 10 metres above the proposed ground level;
schedule 1 paragraph wrapper18 b (b)vortex drop pipe;
schedule 1 paragraph wrapper18 c (c)odour control unit comprising small roadside boxes housing carbon filters and local panels;
schedule 1 paragraph wrapper18 d (d)welfare and laydown area, hard standing and storage area;
schedule 1 paragraph wrapper18 e (e)dewatering;
schedule 1 paragraph wrapper18 f (f)security fencing;
schedule 1 paragraph wrapper18 g (g)soil handling;
schedule 1 paragraph wrapper18 h (h)crane working space;
schedule 1 paragraph wrapper18 i (i)decommissioning works to redundant mains;
schedule 1 paragraph wrapper18 j (j)local control panels;
schedule 1 paragraph wrapper18 k (k)kiosks;
schedule 1 paragraph wrapper18 l (l)closed circuit television cameras and columns;
schedule 1 paragraph wrapper18 m (m)lightning protection infrastructure including masts, finials, earth matts and bonding;
schedule 1 paragraph wrapper18 n (n)chemical storage and dosing plant;
schedule 1 paragraph wrapper18 o (o)a temporary shaft associated with the construction of Work No. 27; and
schedule 1 paragraph wrapper18 p (p)connections to Work Nos. 17, 26 and 27.
Work No. 19 – GATEWAY BUILDING
Gateway building including—
schedule 1 paragraph wrapper19 a (a)office space;
schedule 1 paragraph wrapper19 b (b)welfare facilities;
schedule 1 paragraph wrapper19 c (c)discovery centre;
schedule 1 paragraph wrapper19 d (d)rooftop solar photovoltaic panels;
schedule 1 paragraph wrapper19 e (e)refuse bins;
schedule 1 paragraph wrapper19 f (f)associated plant; and
schedule 1 paragraph wrapper19 g (g)bicycle storage.
Work No. 20 – TEMPORARY COMPOUND AREA
Temporary compound area including welfare facilities.
Work No. 21 – TEMPORARY SITE ESTABLISHMENT
Temporary site establishment and construction works to support construction of Work Nos. 1 to 16, 27, 31, 33, 35 and 36 including—
schedule 1 paragraph wrapper21 a (a)temporary site access works from Horningsea Road and to Low Fen Drove Way;
schedule 1 paragraph wrapper21 b (b)working area compound;
schedule 1 paragraph wrapper21 c (c)concrete batching plant;
schedule 1 paragraph wrapper21 d (d)temporary lined lagoon; and
schedule 1 paragraph wrapper21 e (e)hard standing, laydown and storage.
Work No. 22 – WASTE WATER TREATMENT PLANT CONSTRUCTION WORKS AREA
Construction and material storage area during construction of Work Nos. 1 to 16, 27, 31, 33, 35 and 36.
Work No. 23 – LANDSCAPING AND ECOLOGICAL WORKS
Permanent landscaping and ecological works, including—
schedule 1 paragraph wrapper23 a (a)planting;
schedule 1 paragraph wrapper23 b (b)earthworks and ground re-profiling;
schedule 1 paragraph wrapper23 c (c)drainage works; and
schedule 1 paragraph wrapper23 d (d)creation of footpaths.
Work No. 24 – LANDSCAPING AND ECOLOGICAL WORKS TEMPORARY WORK
Temporary access and working area to support and facilitate the landscaping and ecological works in Work No. 23.
Work No. 25 – TEMPORARY WORKING AREA COMPOUND
Temporary working area compound including welfare facilities.
Work No. 26 – DIVERSION OF RIVERSIDE TUNNEL
Works to divert the existing riverside sewer to connect to Work No. 18 comprising—
schedule 1 paragraph wrapper26 a (a)temporary diversion works including a temporary shaft/pit and temporary overground pipes, underground pipework to connect the Riverside sewer to Work No. 18;
schedule 1 paragraph wrapper26 b (b)installation of temporary pumps and power supply including generators and fuel storage;
schedule 1 paragraph wrapper26 c (c)removal of temporary works; and
schedule 1 paragraph wrapper26 d (d)decommissioning works to the redundant sewer.
Work No. 27 – TRANSFER TUNNEL
An underground transfer tunnel between Work No. 18 and Work No. 16 installed using pipe jacking and including—
schedule 1 paragraph wrapper27 a (a)a temporary construction shaft within each of the areas to which Work No. 27 overlaps with Work No. 28; and
schedule 1 paragraph wrapper27 b (b)connections to Work Nos. 16 and 18.
Work No. 28 – TRANSFER TUNNEL CONSTRUCTION AREA TEMPORARY COMPOUNDS
Temporary working area compounds associated with Work No. 27, including—
schedule 1 paragraph wrapper28 a (a)welfare and laydown areas;
schedule 1 paragraph wrapper28 b (b)crane working space;
schedule 1 paragraph wrapper28 c (c)hard standing;
schedule 1 paragraph wrapper28 d (d)dewatering;
schedule 1 paragraph wrapper28 e (e)security fencing;
schedule 1 paragraph wrapper28 f (f)mud and soil handling; and
schedule 1 paragraph wrapper28 g (g)storage area.
Work No. 29 – TEMPORARY ACCESS WORKS TO WORKS 28, 34 & 36 (WEST OF HORNINGSEA ROAD)
Temporary access works from Horningsea Road to Work Nos. 28, 34 and 36 between Green End and Horningsea Road, with provision for early works access off Poplar Hall private access to facilitate creation, from the field to the west, of the new haul route access off the west side of B1047 Horningsea Road.
Work No. 30 – NETWORK RAIL MONITORING WORKS
Temporary access and monitoring of ground movement at varying depths to railway tracks on Network Rail land and other monitoring due to pipeline and tunnel crossings under the Cambridge to King’s Lynn railway line.
Work No. 31 – FINAL EFFLUENT & STORM PIPELINE
Two outfall pipes to be laid below ground for final effluent and storm water connecting Work No. 12 to Work No. 32 together with associated access and venting manholes and access works from Horningsea Road.
Work No. 32 - OUTFALL
Outfall works in connection with the discharge of final effluent and storm water to the river Cam comprising—
schedule 1 paragraph wrapper32 a (a)two outfall pipes to be laid below ground for final effluent and storm water connecting to Work No. 31;
schedule 1 paragraph wrapper32 b (b)ditch crossing, diversion and associated protection works;
schedule 1 paragraph wrapper32 c (c)temporary access track;
schedule 1 paragraph wrapper32 d (d)temporary working area compound;
schedule 1 paragraph wrapper32 e (e)temporary cofferdam;
schedule 1 paragraph wrapper32 f (f)outfall structure and associated fittings;
schedule 1 paragraph wrapper32 g (g)river bed and embankment reinforcement works including dredging and scour protection measures; and
schedule 1 paragraph wrapper32 h (h)temporary public right of way diversion and restoration works.
Work No. 33 – WATERBEACH PIPELINE NORTH
Up to two waste water pipelines laid underground between a point of connection with waste water infrastructure to be provided as part of the Waterbeach New Town development and Work No. 35 and Work No. 36, including—
schedule 1 paragraph wrapper33 a (a)crossings of the river Cam, the King’s Lynn railway line and Low Fen Drove Way using horizontal directional drilling technique in accordance with the code of construction practice, but otherwise laid using either open cut trenching or horizontal directional drilling technique;
schedule 1 paragraph wrapper33 b (b)new accesses and access improvements;
schedule 1 paragraph wrapper33 c (c)temporary shafts;
schedule 1 paragraph wrapper33 d (d)horizontal directional drilling launch and exit pits;
schedule 1 paragraph wrapper33 e (e)welfare, storage and laydown areas;
schedule 1 paragraph wrapper33 f (f)temporary haul roads;
schedule 1 paragraph wrapper33 g (g)dewatering, drainage works and restoration of existing land drainage;
schedule 1 paragraph wrapper33 h (h)ditch crossing, diversion and associated protection works;
schedule 1 paragraph wrapper33 i (i)mud and soil handling;
schedule 1 paragraph wrapper33 j (j)associated infrastructure including air valves and other pipework fittings and fixtures;
schedule 1 paragraph wrapper33 k (k)permanent accesses for future maintenance and replacement of the pipelines; and
schedule 1 paragraph wrapper33 l (l)connections to Work No. 35 and Work No. 36.
Work No. 34 – WATERBEACH PIPELINE CONSTRUCTION AREA AND COMPOUNDS
Temporary construction compounds, welfare, storage and laydown areas and temporary haul roads in connection with Work Nos. 33, 35 and 36.
Work No. 35 – WATERBEACH PIPELINE SPUR TO TERMINAL PUMPING STATION
Up to two waste water pipelines laid underground between Work No. 33 or 36 and Work No. 16 to facilitate a connection between the waste water infrastructure to be provided as part of the Waterbeach New Town development and Work No. 16 including—
schedule 1 paragraph wrapper35 a (a)crossings using either pipe-jacking or horizontal directional drilling technique but otherwise laid using either open cut trenching or horizontal drilling technique;
schedule 1 paragraph wrapper35 b (b)new accesses and access improvements;
schedule 1 paragraph wrapper35 c (c)temporary shafts;
schedule 1 paragraph wrapper35 d (d)horizontal directional drilling launch and exit pits;
schedule 1 paragraph wrapper35 e (e)welfare, storage and laydown areas;
schedule 1 paragraph wrapper35 f (f)temporary haul roads;
schedule 1 paragraph wrapper35 g (g)construction compounds;
schedule 1 paragraph wrapper35 h (h)dewatering, drainage works and restoration of existing land drainage;
schedule 1 paragraph wrapper35 i (i)ditch crossing, diversion and associated protection works;
schedule 1 paragraph wrapper35 j (j)mud and soil handling;
schedule 1 paragraph wrapper35 k (k)associated infrastructure including air valves and other pipework fittings and fixtures;
schedule 1 paragraph wrapper35 l (l)permanent accesses for future maintenance and replacement of the pipelines; and
schedule 1 paragraph wrapper35 m (m)connections to Work No. 16 and Work Nos. 33 and/or 36.
Work No. 36 – WATERBEACH PIPELINE SOUTH
The provision of the Waterbeach pipeline south works as follows—
schedule 1 paragraph wrapper36 a (a)up to two waste water pipelines laid between Work No. 33 and the boundary of the existing Cambridge waste water treatment works including crossings of the river Cam, the A14, Horningsea Road, Fen Road and the King’s Lynn railway line using horizontal directional drilling technique in accordance with the code of construction practice, but otherwise laid using either open cut tracking or horizontal directional drilling technique;
schedule 1 paragraph wrapper36 b (b)up to two waste water pipelines laid underground and above ground within the existing Cambridge waste water treatment works;
schedule 1 paragraph wrapper36 c (c)new accesses and access improvements;
schedule 1 paragraph wrapper36 d (d)temporary shafts;
schedule 1 paragraph wrapper36 e (e)horizontal directional drilling launch and exit pits;
schedule 1 paragraph wrapper36 f (f)welfare, storage and laydown areas;
schedule 1 paragraph wrapper36 g (g)temporary haul roads;
schedule 1 paragraph wrapper36 h (h)dewatering, drainage works and restoration of existing land drainage;
schedule 1 paragraph wrapper36 i (i)ditch crossing, diversion and associated protection works;
schedule 1 paragraph wrapper36 j (j)mud and soil handling;
schedule 1 paragraph wrapper36 k (k)associated infrastructure including air valves and other pipework fittings and fixtures;
schedule 1 paragraph wrapper36 l (l)permanent accesses for future maintenance and replacement of the pipelines;
schedule 1 paragraph wrapper36 m (m)connections to Work Nos. 33 and 35 and at the existing Cambridge waste water treatment works; and
schedule 1 paragraph wrapper36 n (n)decommissioning of all or part of this Work.
Work No. 37 – TEMPORARY ACCESS WORKS FOR WORK Nos. 33 & 34
Temporary access works associated with Work Nos. 33 and 34 including temporary construction and commissioning dewatering and drainage works, and works to facilitate discharge into the watercourses adjacent to Bannold Drove, Burgess’s Road and Bannold Road.
Work No. 38 – NEW BRIDLEWAY
Works relating to the provision of a new bridleway including street apparatus, gates and signage.
Work No. 39 – ECOLOGICAL MITIGATION AREA
Ecological mitigation works, including—
schedule 1 paragraph wrapper39 a (a)earthworks and ground re-profiling;
schedule 1 paragraph wrapper39 b (b)creation of natural drainage ditches, wetland habitat and ponds;
schedule 1 paragraph wrapper39 c (c)creation of connections to or culverts/bridges over existing drainage ditches;
schedule 1 paragraph wrapper39 d (d)creation of maintenance access routes; and
schedule 1 paragraph wrapper39 e (e)temporary welfare and laydown areas and haul roads.
Work No. 40 – DECOMMISSIONING EXISTING CAMBRIDGE WASTE WATER TREATMENT WORKS
Works to the existing Cambridge waste water treatment works to cease its existing operational function and to facilitate the surrender of its operational permits including—
schedule 1 paragraph wrapper40 a (a)removal of pumps;
schedule 1 paragraph wrapper40 b (b)isolation of plant;
schedule 1 paragraph wrapper40 c (c)isolation of electrical connections;
schedule 1 paragraph wrapper40 d (d)isolation, filling and capping of pipework;
schedule 1 paragraph wrapper40 e (e)cleaning of tanks, pipes, screens and other structures, plant and machinery;
schedule 1 paragraph wrapper40 f (f)works to decommission the potable water supply; and
schedule 1 paragraph wrapper40 g (g)works to restrict access to walkways, plant and machinery.
Further works
In connection with Work Nos. 1 - 40 above and to the extent that they do not form any part of such work, further associated development within the Order limits comprising such other works as may be necessary or expedient for the purpose of or in connection with the relevant part of the authorised development and which fall within the scope of work assessed by the environmental statement including—
(1) In connection with Work Nos. 1 – 37, 39 and 40—
schedule 1 paragraph wrapper41 1 a (a)highways works, including diversions, kerb alterations, white lining, road markings, re-surfacing, laybys, traffic calming, vegetation clearance, traffic management and turning areas;
schedule 1 paragraph wrapper41 1 b (b)road and traffic signage;
schedule 1 paragraph wrapper41 1 c (c)footpaths;
schedule 1 paragraph wrapper41 1 d (d)fencing, security and safety measures including closed-circuit television (CCTV) cameras and columns;
schedule 1 paragraph wrapper41 1 e (e)access gates;
schedule 1 paragraph wrapper41 1 f (f)drainage including attenuation tanks, manholes, highways drainage and internal road drainage, land drainage restoration and diversion, ground and surface water treatment facilities, soakaways and swales and other sustainable drainage systems;
schedule 1 paragraph wrapper41 1 g (g)chemical dosing pipework;
schedule 1 paragraph wrapper41 1 h (h)operational and maintenance task lighting;
schedule 1 paragraph wrapper41 1 i (i)communication and control infrastructure;
schedule 1 paragraph wrapper41 1 j (j)telemetry infrastructure including outstations;
schedule 1 paragraph wrapper41 1 k (k)hard and soft landscaping;
schedule 1 paragraph wrapper41 1 l (l)vehicle restraint systems;
schedule 1 paragraph wrapper41 1 m (m)works within the existing sewers, chambers and culverts and other structures that comprise the existing sewerage network for the purposes of enabling the authorised development, including reconfiguring, modifying, altering, repairing, strengthening or reinstating the existing network;
schedule 1 paragraph wrapper41 1 n (n)works within new and existing pumping stations including structural alterations to the interior fabric of the pumping station(s), works to reconfigure existing pipework, provision of new pipework, new penstock valves and associated equipment, modification of existing electrical, mechanical and control equipment, and installation or provision of new electrical, mechanical and control equipment;
schedule 1 paragraph wrapper41 1 o (o)installation of electrical, mechanical and control equipment in other buildings and kiosks and modification to existing electrical, mechanical and control equipment in such buildings and kiosks;
schedule 1 paragraph wrapper41 1 p (p)installation of pumps in chambers and buildings;
schedule 1 paragraph wrapper41 1 q (q)works to trees and landscaping works not comprising development;
schedule 1 paragraph wrapper41 1 r (r)works associated with monitoring of buildings and structures;
schedule 1 paragraph wrapper41 1 s (s)works required for the strengthening, improvement, maintenance or reconstruction of any street;
schedule 1 paragraph wrapper41 1 t (t)works to place, alter, remove or maintain street furniture or apparatus in a street, or apparatus in other land, including mains, sewers, drains, soakaways, pipes, cables and ducts; and
schedule 1 paragraph wrapper41 1 u (u)works to install, divert, repair, replace, maintain and decommission gas, potable water, waste water, electricity and telecommunications services and apparatus.
(2) In connection with Work Nos. 1 – 40, temporary works relating to construction including—
schedule 1 paragraph wrapper41 2 a (a)lighting;
schedule 1 paragraph wrapper41 2 b (b)ramps, accesses, non-motorised links, and crossing facilities;
schedule 1 paragraph wrapper41 2 c (c)welfare facilities including generators; and
schedule 1 paragraph wrapper41 2 d (d)security measures including fencing and CCTV.
(3) Within the area of such works which are 30 metres in any direction from the river Cam, works relating to the suspension of existing moorings and the relocation of boats/vessels including works to attach mooring structures and equipment to the boats/vessels.
(4) Within the inner boundary of Work No. 15—
schedule 1 paragraph wrapper41 4 a (a)internal access and circulation roads, turning areas, hardstanding, and parking;
schedule 1 paragraph wrapper41 4 b (b)air, steam and hot water distribution infrastructure;
schedule 1 paragraph wrapper41 4 c (c)motor control centres;
schedule 1 paragraph wrapper41 4 d (d)local control panels;
schedule 1 paragraph wrapper41 4 e (e)programmable logic controllers;
schedule 1 paragraph wrapper41 4 f (f)high voltage switchgears and transformers;
schedule 1 paragraph wrapper41 4 g (g)solar photovoltaic panels;
schedule 1 paragraph wrapper41 4 h (h)switchgear buildings, battery storage buildings and associated connections to the solar photovoltaic panels installed in connection with Work Nos. 7, 15 and 19;
schedule 1 paragraph wrapper41 4 i (i)kiosks;
schedule 1 paragraph wrapper41 4 j (j)gas infrastructure;
schedule 1 paragraph wrapper41 4 k (k)closed-circuit television cameras and columns;
schedule 1 paragraph wrapper41 4 l (l)odour ducting and treatment; and
schedule 1 paragraph wrapper41 4 m (m)lightning protection infrastructure including masts, finials, earth matts and bonding.
(5) Works associated with decommissioning the existing Cambridge waste water treatment works including the existing outfall north of the A14 and assets in Cowley Road, and the existing Waterbeach Wastewater Treatment Works and diversions of existing utilities and services.
Section 35 was amended by section 26(2) of the Growth and Infrastructure Act 2013 (c. 27).